St. Marienwörth Hospital, renovation of the bed house in component A to C, level +3, sanitary installation.
— approx. 270 m cast iron and plastic drainage lines
— approx. 565 m drinking water pipes made of stainless steel and plastic, with thermal insulation,
— approx. 13 pieces of installation system walls with fire protection
— Approximately 74 pieces of sanitary objects with hygiene devices.
Estimated execution times:
— Implementation period 1 BA: September 2021 to April 2022,
— Implementation period 2 BA: May 2022 to January 2023,
— Implementation period 2 BA: February 2023 to July 2023.