The overall project consists of the new construction of R+2 offices as well as underground parking spaces.
Estimated budget: EUR 2,721,550.00 excl. VAT
The tasks entrusted to the incumbent are as follows:
- Phase 1 : Esquisse (left) ;
- Phase 2: Preliminary design (APS);
- Phase 3: Final Preliminary Design (APD);
- Phase 4: project studies (Pro);
- Phase 5: Assistance with the award of works contracts (Amt);
- Phase 6: total execution and synthesis studies (Total Exe including Visa);
- Phase 7: Construction Execution Management (Det);
- Phase 8: Scheduling, Steering and Coordination (OPC);
- Phase 9: Assistance with receiving operations (Aor including Doe);
- Phase 10: Coordination of the fire safety system (CSSI) - additional mission.
The overall project consists of the new construction of R+2 offices as well as underground parking spaces.
Estimated budget: EUR 2,721,550.00 excl. VAT
The tasks entrusted to the incumbent are as follows:
- Phase 1 : Esquisse (left) ;
- Phase 2: Preliminary design (APS);
- Phase 3: Final Preliminary Design (APD);
- Phase 4: project studies (Pro);
- Phase 5: Assistance with the award of works contracts (Amt);
- Phase 6: total execution and synthesis studies (Total Exe including Visa);
- Phase 7: Construction Execution Management (Det);
- Phase 8: Scheduling, Steering and Coordination (OPC);
- Phase 9: Assistance with receiving operations (Aor including Doe);
- Phase 10: Coordination of the fire safety system (CSSI) - additional mission.