The proposed development works to the Brewhouse Building to facilitate its conversion to a range of uses including education, research and development, and/or office facility consists of:
— the retention and re-use of the brewhouse building (approx. 4,530 m
— the demolition of a 2 storey steel framed extension to the south of the original ‘Bauhaus’ structure.(855 m
— construction of a new 220 m
— insertion of new floors in voids at first and second floor level to create additional floor space within the existing building envelope.
Replacement of part of the existing roof structure:
— this building is to be constructed to a L.E.E.D Gold certified standard.
The proposed development works to the brewhouse building to facilitate its conversion to a range of uses including education, research and development, and/or office facility consists of:
— the retention and re-use of the Brewhouse Building (approx. 4,530 m
— the demolition of a 2 storey steel framed extension to the south of the original ‘Bauhaus’ structure.(855 m
— construction of a new 220 m
— insertion of new floors in voids at first and second floor level to create additional floor space within the existing building envelope.
Replacement of part of the existing roof structure:
— this building is to be constructed to a L.E.E.D Gold certified standard.