Heating, ventilation and sanitary installations, electrical installations and kitchen equipment.
- 2 heat pumps of 34 kW,
- geothermal installation 15 boreholes,
- solar hot water installation,
- 1,200 m
- 1,230 m heating piping,
- ventilation system 13,600 m
- set of regulation equipment, electrical panels, wiring,
- 55 sanitary appliances,
- 1,100 m water distribution piping,
- 250 m waste water pipeline,
- dry column.
The start of work is scheduled for March 2020. The duration of the work is 170 working days (in phases).
- 8 distribution boards,
- surge arrester installation,
- 180 m cable trays,
- 600 switches and sockets,
- 270 indoor / outdoor lights,
- 100 safety lights with autonomous battery,
- fire detection + 220 detectors,
- smoke extraction installation,
- computer rack + 55 data and wiring sockets,
- sun protection,
- 22.5 kWp photovoltaic system,
- double charging station 2 × 22 kW.
The start of work is scheduled for March 2020. The duration of the work is 185 working days (in phases).
- production capacity 200 meals,
- delivery and unpacking area, neutral furniture,
- dry storage, shelves,
- 3 cold rooms,
- vegetables, neutral furniture,
- cold preparations,
- hot preparations,
- refrigerated cabinets,
- sink, laundromat, dishwasher,
- electromechanical equipment,
- educational cooking.
Supply of plans: March 2020. Start of works: October 2020. Duration of works: 15 working days.