Installation of bathing water technology with filters, blowers, pumps, treatment and piping
Description Bathing Water Technology BT A-D
Type and scope of the object of the order:
The construction project involves the renovation, modernization and expansion of the wish spa in Winnenden.
Here especially the bathing water technology for the components A-D main building and course pool
Main building Renovation and extension: Two-storey and partial basement
New course pool: single-storey with basement
Course pool (new building)
• Complete treatment plant for the 25 m course pool consisting of:
o 2 GRP multilayer filters (D = 2.4 m) incl. filter material
o Purge air blower for the two filters
o 2 pcs circulation pumps with 170 m3/h each in backwash mode
o Measuring and dosing station incl. extension of the existing chlorine gas plant by the connection of the new processing plant
• Finishing parts in the basin (nozzles, mesh covers)
• Piping of the tanks, the water treatment and the pool components (these are installed by the customer)
Children's pool (new building)
• Piping of the pool components, which are installed on site), to existing circulation circuit.
• New splash water pipe incl. new connection to existing surge water tank
• New measuring water station.
• Finishing parts in the basin (nozzles, mesh covers)
Plunge pool (new construction/refurbishment)
• Piping of the existing preparation plant with the new basin (basin components on site)
• New measuring water station
• Finishing parts in the basin (nozzles, mesh covers)
Piping and Miscellaneous
• In total approx. 500 m PE-HD pipeline da 40 to da 315 plus fittings
• Renewal of all BWT heat exchangers; approx. 6 pcs
• Various driving water pumps; Injectors etc.
Performance dates:
Execution period: April 2023 to May 2024
Completion of new opening 01.06.2024