Delivery, installation and commissioning of a ship connection system for the expansion of the shore power plant at the Ostseekai, Kiel.
The service component of the tender is the planning, procurement and construction of a mobile,
self-propelled, battery-powered ship connection system 11kV/16 MVA or 6.6kV/10 MVA and 50/60Hz
according to IEC 80005-1 standard as an automated transfer device between existing junction boxes and
MV input switchgear on the cruise ship to be supplied. Furthermore, participation in the
Preparation of the design/approval planning on the basis of preliminary planning, as well as participation in the
commissioning and certification tests are part of the contractor's service.