The object of the contract consists of the supply of charging stations and installation works for the investment objective "Charging stations for electric vehicles in Vaslui County", in the quantities and with the specifications provided in the specifications.
Through this procedure, the aim is to purchase and install charging stations for electric vehicles (13 fast charging stations DC/AC minimum 82 KW and 1 Multistandard fast charging station DC/AC minimum 82 KW).
The equipment to be purchased through this procedure will be reliable and economical, suitable for intensive use (24 hours/day, 7 days a week) for the entire duration of use (including during the warranty period). Only new, unused, state-of-the-art equipment manufactured in 2024 or later will be accepted.
The winning bidder will ensure the supply, installation, commissioning, staff training, and service during the warranty period for the supplied equipment.
The general objective of the procurement consists of the procurement, installation, and commissioning of a total of 14 charging stations for electric vehicles (realization of electrical connections, realization of electrical installations, supply/installation/mounting/commissioning of 14 charging stations, realization and installation of information panels, and arrangement of parking spaces related to the 14 charging stations).
Vaslui County initiated the project "Charging stations for electric vehicles in Vaslui County" and obtained financing through the Environmental Fund Administration. The project provides for the installation of 14 charging stations for electric vehicles, distributed at 7 locations in the county, one of which will be a Multistandard fast charging station.
At the 7 locations, the charging stations will be equipped with one DC charging point (one connector) of at least 60 kW and one AC charging point (one connector) of at least 22 kW.
NOTE:
Any reference in the procurement documents that indicates a specific origin, source, production, manufacturer, special process, standard, regulation, trade mark or brand, patent, manufacturing license, are mentioned only for the purpose of easily identifying the types of product as a concept and do not have the effect of favoring or eliminating certain economic operators or certain products/services or works. These specifications will be considered as having the mention of "or equivalent", and the bidder has the obligation to demonstrate the equivalence of the offered products/services/works with those requested, if applicable.
NOTE: The deadline by which any interested economic operator has the right to request clarifications or additional information regarding the award documentation is 19 days before the deadline for submission of offers. The contracting authority will respond clearly and completely to all requests for clarifications on the 11th day before the deadline set for submission of offers.
NOTE: Requests for clarifications regarding this award documentation should be addressed exclusively to SEAP in the "Questions" section within the electronic awarding procedure, and responses will be published in SEAP in the "Procedure Details - Clarifications, decisions on the award documentation" section of the simplified participation announcement, with the contracting authority not responding to requests submitted through any other communication method than the established one.
LOT-0000
Default lot.
(nature and quantity of works, products or services or a mention regarding needs and requirements)
The object of the contract consists of the supply of charging stations and installation works for the investment objective "Charging stations for electric vehicles in Vaslui County", in the quantities and with the specifications provided in the specifications.
Through this procedure, the aim is to purchase and install charging stations for electric vehicles (13 fast charging stations DC/AC minimum 82 KW and 1 Multistandard fast charging station DC/AC minimum 82 KW).
The equipment to be purchased through this procedure will be reliable and economical, suitable for intensive use (24 hours/day, 7 days a week) for the entire duration of use (including during the warranty period). Only new, unused, state-of-the-art equipment manufactured in 2024 or later will be accepted.
The winning bidder will ensure the supply, installation, commissioning, staff training, and service during the warranty period for the supplied equipment.
The general objective of the procurement consists of the procurement, installation, and commissioning of a total of 14 charging stations for electric vehicles (realization of electrical connections, realization of electrical installations, supply/installation/mounting/commissioning of 14 charging stations, realization and installation of information panels, and arrangement of parking spaces related to the 14 charging stations).
Vaslui County developed the project "Charging stations for electric vehicles in Vaslui County", obtaining financing from the Environmental Fund Administration for the placement of 14 charging stations for electric vehicles in 7 locations in the county (of which one is a Multistandard fast charging station).
At the 7 locations, the charging stations will be equipped with one DC charging point (one connector) of at least 60 kW and one AC charging point (one connector) of at least 22 kW.