Installation of a PV system for the charging area.
LOT-0000
Delbus PV system.
The PV system is to be installed above the steel structure of the media bridges in the charging area. In the first construction phase, approximately 56 kWp are to be set up on a double field of the media bridges. Overall, the charging area has 5 double fields, which can also be equipped with PV modules at a later date. The initial installation must be expandable, and the inverters in the ZBV room (LS 007) must be arranged so that the system can be expanded without remodeling work at a later date. The PV system is to be electrically integrated into the NS system in the charging area. The 56 kWp output should primarily cover the needs of the workshop operations and the consumption in the operational service building. A battery storage system is also to be installed.
For more information, please refer to the specifications.
Dates:
Installation of PV modules with cable installation work: 06.04.2026 - 30.04.2026
Installation of inverters and connection to the NSHV main distribution: 01.06.2026 - 19.06.2026