The subject of the order includes the delivery, installation, and commissioning of photovoltaic systems and energy storage in public utility buildings in the Kraśnik District as part of the task "Installation of Photovoltaic Systems on Buildings of the Kraśnik District - Part I." The installations are to be carried out in the following buildings:
1) Community Support Home in Kraśnik - photovoltaic installation with a power of min. 34.32 kWp and energy storage with a capacity of 50 kWh,
2) Special School Complex in Kraśnik - photovoltaic installation with a power of min. 17.68 kWp, energy storage with a capacity of 30 kWh,
3) Care and Educational Facility No. 1 in Kraśnik - photovoltaic installation with a power of min. 27.04 kWp, energy storage with a capacity of 50 kWh,
4) School Complex No. 2 in Kraśnik:
a) School Complex No. 2 in Kraśnik (School) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
b) School Complex No. 2 in Kraśnik (Hall) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
c) School Complex No. 2 in Kraśnik (Dormitory) - photovoltaic installation with a power of min. 15.08 kWp, energy storage with a minimum capacity of 30 kWh,
5) School Complex No. 3 in Kraśnik (CKZ) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
6) District Office in Kraśnik - Geodesy Department - photovoltaic installation with a power of min. 22.88 kWp, energy storage with a minimum capacity of 50 kWh,
The scope of the subject of the order for the above-mentioned locations includes, in particular:
- installation of structures for PV panels,
- installation of PV panels on the structure,
- installation of inverters and energy storage,
- laying of cable routes and cables from PV panels to the electrical distribution board,
- connection to the cable junction,
- installation of DC switchboards RPV1, RPV2
- installation of AC switchboard RAC,
- performing installation tests and verifying the correct operation of the equipment,
- commissioning the system and adjustments,
- training on operation.
LOT-0001
Installation of Photovoltaic Systems on Buildings of the Kraśnik District – Part I.
The subject of the order includes the delivery, installation, and commissioning of photovoltaic systems and energy storage in public utility buildings in the Kraśnik District as part of the task "Installation of Photovoltaic Systems on Buildings of the Kraśnik District – Part I." The installations are to be carried out in the following buildings:
1) Community Support Home in Kraśnik - photovoltaic installation with a power of min. 34.32 kWp and energy storage with a capacity of 50 kWh,
2) Special School Complex in Kraśnik - photovoltaic installation with a power of min. 17.68 kWp, energy storage with a capacity of 30 kWh,
3) Care and Educational Facility No. 1 in Kraśnik - photovoltaic installation with a power of min. 27.04 kWp, energy storage with a capacity of 50 kWh,
4) School Complex No. 2 in Kraśnik:
a) School Complex No. 2 in Kraśnik (School) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
b) School Complex No. 2 in Kraśnik (Hall) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
c) School Complex No. 2 in Kraśnik (Dormitory) - photovoltaic installation with a power of min. 15.08 kWp, energy storage with a minimum capacity of 30 kWh,
5) School Complex No. 3 in Kraśnik (CKZ) - photovoltaic installation with a power of min. 34.32 kWp, energy storage with a minimum capacity of 50 kWh,
6) District Office in Kraśnik - Geodesy Department - photovoltaic installation with a power of min. 22.88 kWp, energy storage with a minimum capacity of 50 kWh,
The scope of the subject of the order for the above-mentioned locations includes, in particular:
- installation of structures for PV panels,
- installation of PV panels on the structure,
- installation of inverters and energy storage,
- laying of cable routes and cables from PV panels to the electrical distribution board,
- connection to the cable junction,
- installation of DC switchboards RPV1, RPV2
- installation of AC switchboard RAC,
- performing installation tests and verifying the correct operation of the equipment,
- commissioning the system and adjustments,
- training on operation.