Delivery of a grid-connected battery storage system to FL-9496 Balzers with at least 25 MW / 50 MWh
LOT-6731
Battery storage system (BESS) Balzers.
The Liechtenstein Electric Power Company wants to procure a battery storage system (BESS) with at least 25 MW / 50 MWh. Delivery will take place to FL-9496 Balzers. A building permit for the construction of the BESS is already in place, which sets the framework for the maximum volume. The bidder will deliver the components to the site, where they will be brought in and wired by the trucks. Commissioning will also be carried out by the bidder.
The specified contract duration of 132 months includes a maximum execution period of 12 months until commissioning and the mandatory warranty and service phase of 120 months as stipulated in the draft contract.