VE 04 - Charging Technology
LOT-0000
Bus Depot Lindenau, Expansion of Charging Infrastructure, VE 04 - Charging Technology.
Establishing a charging infrastructure for charging electric buses with pantographs and partially plug charging, consisting of
- 5 pcs multiple chargers at 600 kW
- 2 pcs multiple chargers at 400 kW
- 40 pcs dispensers for charging hoods
- 38 pcs charging hoods
Delivery and installation of multiple chargers and charging hoods with dispensers as well as dispensers with charging connectors;
Complete wiring of the charging infrastructure on and in existing routes, pipes, and risers;
Multiple modifications of existing charging technology (Siemens), relocating existing charging points including wiring (charging hoods from Schunk);
Temporary installation of a new multiple charger 600 kW with wiring;
Installation of charging hoods on existing mounting plates on trusses;
Establishing the complete data wiring of the charging infrastructure;
Linking the charging technology with the site operations management systems;
Parameterization of the entire charging technology;
Creating checklists for partial commissioning and overall commissioning;
Commissioning in multiple phases