The new medium voltage system will be planned as a customer-owned facility. It consists of a medium voltage switchgear with branch feeding, 1 outgoing field, and 1 transformer. The preliminary power requirement is approx. 1400 kVA. The system is designed for a maximum power of 1600 kVA, with the transformer connected at 1600 kVA. A remote control device for grid-side control of energy generation plants will be included in the planning. With the currently planned output of renewable energies, a grid and facility protection (NA protection) is sufficient. The central disconnection protection between the generating plant and grid connection (on the MV side) has also been planned.
This also includes the UPS with a bridging time of 8 hours.
Milestone dates and content of construction execution:
1. Start of work: approx. 15.06.26
2. Completion TSH: 13.08.27
3. Completion of renovation and sauna extension: 26.11.27
(each including commissioning, trial operation, partial/full acceptance tests, follow-up work)
LOT-0000
BLH, MidSommerland, Medium Voltage System (XA-25/0007-053.2/TSB).
The new medium voltage system will be planned as a customer-owned facility. It consists of a medium voltage switchgear with branch feeding, 1 outgoing field, and 1 transformer. The preliminary power requirement is approx. 1400 kVA. The system is designed for a maximum power of 1600 kVA, with the transformer connected at 1600 kVA. A remote control device for grid-side control of energy generation plants will be included in the planning. With the currently planned output of renewable energies, a grid and facility protection (NA protection) is sufficient. The central disconnection protection between the generating plant and grid connection (on the MV side) has also been planned.
This also includes the UPS with a bridging time of 8 hours.
Milestone dates and content of construction execution:
1. Start of work: approx. 15.06.26
2. Completion TSH: 13.08.27
3. Completion of renovation and sauna extension: 26.11.27
(each including commissioning, trial operation, partial/full acceptance tests, follow-up work)