1. The subject of the contract is the modernization and expansion of the wastewater treatment plant in Marczyce (plots No. 11/5, 180/1) as part of Stage I, while simultaneously maintaining the operation of the old facility (plot No. 12/12) and its shutdown after the new installation is commissioned.
2. This contract follows the "Design and Build" formula, which means that the element treated as Stage I is the comprehensive, complete design of the project understood as full design documentation, cost estimates, and technological documentation, along with detailed Technical Specifications for Execution and Acceptance of Construction Works (STWiORB/WWiORB) subject to approval by the Contracting Authority, and other unspecified but necessary items for the proper commissioning of the facility, as well as obtaining decisions, permits, and other legal documents required for this type of facility.
3. The subject of the contract in the "Design and Build" formula includes the physical and full-scope execution of Stage I of the investment ensuring full technological functionality of the facility for a capacity of 12,500 RLM, whereby the Contractor is obliged to include in the design documentation and execute in the infrastructure of Stage I reserved land and technical provisions for potential future expansion according to the following principles:
1) Design documentation (construction, technical and executive projects) developed by the Contractor relates exclusively to the facilities and installations implemented within Stage I.
2) At the planning and site arrangement stage, the Contractor must foresee spatial and land reserves, meaning such placement of Stage I facilities on the investment site to enable collision-free future expansion of the treatment plant with additional technological lines without the need to demolish or reconstruct the infrastructure built under this contract.
3) In the installation scope, the Contractor must design and execute within Stage I physical technical reserves prepared for future connection of the expansion, which means an absolute obligation to install blind flanges, shut-off valves, free connection stub pipes on pipelines and collector systems, as well as leaving power reserve on main switchboards, free cable routes, and at least 25% spatial and signal reserve in control cabinets and the overarching SCADA system.
4. The subject of the contract - Stage 1 - involves the construction of a new mechanical-biological wastewater treatment plant in Marczyce on plots No. 11/5, 180/1, with a capacity of RLM = 12,500 and average daily throughput Qd = 1,630 m³/day. This stage includes ensuring full acceptance of transported sewage up to 100 m³/day and their dynamic buffering (through synchronized operation of the pumping station and emptying pumps) using an existing retention facility adapted for this purpose. Safe acceptance of increased peak flows during intense rainfall events up to Qm = 280 m³/h (77.8 l/s).
This stage also includes maintaining continuous operation of the existing facility on plot No. 12/12 and its complete shutdown and maintenance after stable commissioning of the new installation. An integral part of Stage I (within the lump sum price) is the complete execution of a system for discharging treated wastewater to the receiver. The basic solution is discharging the treated wastewater into the Czerwonka stream. As part of the implementation, the Contractor must perform a detailed hydrological analysis and capacity analysis of the existing outlet to the Czerwonka stream (for which proceedings to extend the water permit for discharging treated wastewater from the existing plant are underway), regarding the technical feasibility of using it to receive the planned amount of water.
5. If the hydrological and capacity analyses conclude that the existing outlet cannot receive the volume of treated water planned for Stage I, the Contractor is obligated to design and build an alternative complete pressure-gravity system to the Podgórna stream as part of Stage I. This system includes building a pressure pipeline 250PE SDR11 PN16 and a gravity section Dn400 PVC SN8 along with a DN 400 outlet structure in a stone wall at km 3+311 of the Podgórna stream.
6. The subject of the contract includes:
1) in the scope of the basic contract:
a) preparation of design documentation for Stage I (conceptual with consideration of the final state of the wastewater treatment plant (Stage II) land and technical reserves, construction, technical and executive documentation) of the investment along with obtaining necessary agreements, opinions, permits, and decisions, including the building permit,
b) construction of the wastewater treatment plant, training, commissioning, testing, handover for operation and use (a usage permit is required).
2) in the scope of the contract under the option right:
a) construction of a complete pressure-gravity system to the Podgórna stream;
b) resolution of conflicts with overhead 20 kV SN lines will occur if during the design phase the exact location of objects shows physical or normative conflict with the overhead power line of the operator TAURON Dystrybucja S.A.
The detailed description and method of contract execution are contained in the Functional and Utility Program (hereinafter: "PFU") which constitutes Annex No. 11 to the Terms of Reference.
LOT-0001
RI.271.75.2026
Modernization and Expansion of the Wastewater Treatment Plant in Marczyce.
1. The subject of the contract is the modernization and expansion of the wastewater treatment plant in Marczyce (plots No. 11/5, 180/1) as part of Stage I, while simultaneously maintaining the operation of the old facility (plot No. 12/12) and its shutdown after the new installation is commissioned.
2. This contract follows the "Design and Build" formula, which means that the element treated as Stage I is the comprehensive, complete design of the project understood as full design documentation, cost estimates, and technological documentation, along with detailed Technical Specifications for Execution and Acceptance of Construction Works (STWiORB/WWiORB) subject to approval by the Contracting Authority, and other unspecified but necessary items for the proper commissioning of the facility, as well as obtaining decisions, permits, and other legal documents required for this type of facility.
3. The subject of the contract in the "Design and Build" formula includes the physical and full-scope execution of Stage I of the investment ensuring full technological functionality of the facility for a capacity of 12,500 RLM, whereby the Contractor is obliged to include in the design documentation and execute in the infrastructure of Stage I reserved land and technical provisions for potential future expansion according to the following principles:
1) Design documentation (construction, technical and executive projects) developed by the Contractor relates exclusively to the facilities and installations implemented within Stage I.
2) At the planning and site arrangement stage, the Contractor must foresee spatial and land reserves, meaning such placement of Stage I facilities on the investment site to enable collision-free future expansion of the treatment plant with additional technological lines without the need to demolish or reconstruct the infrastructure built under this contract.
3) In the installation scope, the Contractor must design and execute within Stage I physical technical reserves prepared for future connection of the expansion, which means an absolute obligation to install blind flanges, shut-off valves, free connection stub pipes on pipelines and collector systems, as well as leaving power reserve on main switchboards, free cable routes, and at least 25% spatial and signal reserve in control cabinets and the overarching SCADA system.
4. The subject of the contract - Stage 1 - involves the construction of a new mechanical-biological wastewater treatment plant in Marczyce on plots No. 11/5, 180/1, with a capacity of RLM = 12,500 and average daily throughput Qd = 1,630 m³/day. This stage includes ensuring full acceptance of transported sewage up to 100 m³/day and their dynamic buffering (through synchronized operation of the pumping station and emptying pumps) using an existing retention facility adapted for this purpose. Safe acceptance of increased peak flows during intense rainfall events up to Qm = 280 m³/h (77.8 l/s).
This stage also includes maintaining continuous operation of the existing facility on plot No. 12/12 and its complete shutdown and maintenance after stable commissioning of the new installation. An integral part of Stage I (within the lump sum price) is the complete execution of a system for discharging treated wastewater to the receiver. The basic solution is discharging the treated wastewater into the Czerwonka stream. As part of the implementation, the Contractor must perform a detailed hydrological analysis and capacity analysis of the existing outlet to the Czerwonka stream (for which proceedings to extend the water permit for discharging treated wastewater from the existing plant are underway), regarding the technical feasibility of using it to receive the planned amount of water.
5. If the hydrological and capacity analyses conclude that the existing outlet cannot receive the volume of treated water planned for Stage I, the Contractor is obligated to design and build an alternative complete pressure-gravity system to the Podgórna stream as part of Stage I. This system includes building a pressure pipeline 250PE SDR11 PN16 and a gravity section Dn400 PVC SN8 along with a DN 400 outlet structure in a stone wall at km 3+311 of the Podgórna stream.
6. The subject of the contract includes:
1) in the scope of the basic contract:
a) preparation of design documentation for Stage I (conceptual with consideration of the final state of the wastewater treatment plant (Stage II) land and technical reserves, construction, technical and executive documentation) of the investment along with obtaining necessary agreements, opinions, permits, and decisions, including the building permit,
b) construction of the wastewater treatment plant, training, commissioning, testing, handover for operation and use (a usage permit is required).
2) in the scope of the contract under the option right:
a) construction of a complete pressure-gravity system to the Podgórna stream;
b) resolution of conflicts with overhead 20 kV SN lines will occur if during the design phase the exact location of objects shows physical or normative conflict with the overhead power line of the operator TAURON Dystrybucja S.A.
The detailed description and method of contract execution are contained in the Functional and Utility Program (hereinafter: "PFU") which constitutes Annex No. 11 to the Terms of Reference.