Procurement seeks design services and technical assistance for the rehabilitation and modernization of PDA 1 at AIHCB, including railway connections, safety zone arrangements, and rapid release solutions.
The procurement of design services (DTAC, PTE), including technical assistance, and execution works for the investment objective "Rehabilitation and modernization works of PDA 1 at AIHCB, including connections to the railways, related installations, safety zone arrangements for the runway, and achieving the optimal rapid release solution".
Number of days until which clarifications can be requested before the deadline for submitting offers: 18
The contracting authority will respond clearly and completely to all requests for clarification/additional information on the 11th calendar day before the deadline for submitting offers.
LOT-0000
Default lot.
The subject of this procedure is:
- Preparation of design documentation (DTAC, PTE), including technical assistance of the designer during execution and the warranty period of the works. Design documentation will be prepared in accordance with HG no. 907/2016 with subsequent amendments and will comply with the recommendations from the Feasibility Study and the Specifications.
- Execution of works for the investment objective "Rehabilitation and modernization works of PDA 1 at AIHCB, including connections to the railways, related installations, safety zone arrangements for the runway, and achieving the optimal rapid release solution". To reduce the execution time of the works, C.N. AB S.A. may request that the execution of certain categories of works takes place on a 24-hour basis, without the Contractor being able to request additional costs, as these are considered included in the offer.
Duration in months: minimum 85 months, of which:
- Technical project execution drafting and submission deadline: maximum 9 months from the date notified by the Beneficiary/Supervisor regarding the start of the design activity
- Works execution deadline: maximum 16 months from the issuance of the order to commence the works
- Minimum warranty granted for the works: 60 months
Estimated total value: 529,734,227.65 lei, excluding VAT, of which:
- a. Design services (DTAC, PTE) and technical assistance during the execution and warranty period of the works: 17,740,217.44 lei, excluding VAT;
- b. Execution works, including site organization, tests, and inspections: 511,994,010.21 lei, excluding VAT.
The total value of the works may include miscellaneous and unforeseen expenses of 20% of the offered value. THIS PERCENTAGE IS NOT SUBJECT TO BIDDING.