TW - Battery Storage Zengermoos - Construction Battery Storage Zengermoos
LOT-0000
SV-KWE-261023-002
SV-KWE-261023-002 - TW - Battery Storage Zengermoos - Construction Battery Storage Zengermoos.
The subject of this tender is the turnkey planning, supply, construction, integration, commissioning, and documentation of two grid-connected battery storage systems (BESS plant) at 2 existing photovoltaic systems (PV systems) of the client.
The battery storage systems will be built as green electricity storage (co-location) with the existing PV systems. Charging of the battery storage from the public grid is not planned in the basic setup. However, the creation of a future expansion option for grid-forming functions according to current FNN guidelines or "gray electricity storage operation" shall be ensured.
The battery storage systems must be electrically integrated into the existing PV systems and operated together with them via the existing grid connection points at the substation of the grid operator Bayernwerk.
The existing PV systems including grid connection, medium-voltage infrastructure, park control, EZA controller, remote control technology, plant certification are to continue to be used and extended accordingly by the contractor.
The contractor owes a fully functional, operational, and certification-capable overall plant condition (PV + BESS plant) including all necessary technical, planning, and administrative services.
After the complete construction and acceptance of the BESS plant, the contractor will perform full maintenance (service activities for maintenance, inspections, troubleshooting or repairs, and spare parts management including warranties) for the BESS plant.